Confidential Client – Natural Gas Plant Truck Loading Facility
Location: Central TX
Matrix PDM Engineering’s project team integrated controls and process systems to design a new truck loading facility in under four months, meeting the client's aggressive time-frame.
The new additions included two truck loading bays, two 90,000 gallon storage tanks, and enclosed flare for vapor incineration, slop tank, sump and pump and other ancillary equipment. The loadout was designed for bottom load trucks with the ability to add two more loading bays in the future.
100%
Commitment to safely meeting deadlines
2x 90000
gallon storage tanks
0
Incident safety culture
Scope of Work
- Enclosed flare skid for vapor combustor
- Truck loading canopy for operators
- Two 90,000 gallon storage tanks
- Concrete containment
- Piping interconnecting the equipment modules